Summary

A motivated electrical engineer, with an extensive experience of working with international team members throughout my career, in an environment of extreme technical complexity, of high scale and of high availability. My passion is to add value to an organization where every day, job responsibilities bring a new challenge to achieve in addition to enhancement in my learning and knowledge.

Experience

Company Logo
ELECTRICAL ENGINEER
Gezhouba Mechanical & Electrical construction co. Ltd (GMEC) Neelum Jhelum Hydro Electric Power Pr
Apr 2014 - Present | Muzaffarabad, Pakistan

• My job comprises detail supervision & monitoring of erection/installation testing & commissioning of all Electrical Equipment. Contract documents preparations, design review & Progress monitoring during constructions.
• To manage and implement delegated aspects of the Quality / HSE management systems and control site supervision in support of the Senior Engineer, QA/QC Manager and Project manager in their implementation of Site Operations department goals for performance improvement and completion of project functions.
• To be constantly aware of all continuing operations on the site by means of regular site visits.
• Follow up mobilization and de-mobilization arrangements at site
• Direct the junior in their daily duties.
• Liaison with and coordinate with all technical disciplines. I.e. civil, mechanical, geology department
• Regularly attend progress, technical, safety and co-ordination meetings
• Coordination with Client (WAPDA) and Consultant (NESPAK, NDC & ACE) Representatives.
• Coordination with local officials, AJK administration and labor union.
• Installation and commissioning of Diesel Generator, Excitation transformer, main Auxiliary power transformer, grounding transformer of Generators, inlet valves, servo motors, governor, excitation system, cooling water system, compressed air system, DC battery system.
• Member of a team to supervise the installation of unit’s (1,2,3,4) equipment’s according to method statement.
• Installation and commissioning of temperature sensors, flow meter, flow switch, limit switch, vibration sensors, pressure sensors, pressure switch installation and commissioning.
• 11-KV substation.
• Cable laying and cable termination.
• Member of a team to supervise the Installation of Different Equipment in 525kv switchyard and GIS hall.
• Installation of control and protection panels at control Building.
• Earthling of All Electrical equipment’s in control building, switchyard,11kv substation and cables tranches.

Education

University of the Punjab
Bachelors, Bachelors in Technology, Electrical Engineering‎
Electric Power and Control System, Electrical, Electrical Engineering Electronics
CGPA 3.0/4
2014

Skills

Beginner Etap

Languages

Expert Urdu
Intermediate English

Waheed Contacts

Rabia Ghani
Philips Electrical Industries of Pakistan