Construction Of 02 Nos. API 620 Dome Roof Isomerate Storage Tanks NRL Khi.
GAS COMPRESSOR INSTALLATION
DEVELOPMENT OF AMIN WATER INJECTION PRODUCTION STATION
INSTALLATION OF PIPING OF DIFFERENT SIZES FOR FIRE FIGHTING WATER CONNECTIO
MAINTENANCE OF TANK T-932 (24M DIA – FIXED ROOF TANK)
MAINTENANCE OF TANK T-8567 (19M DIA – FLOATING ROOF TANK)
GAS FLOATATION TANK T-7572
CONSTRUCTION OF A NEW OIL DEPOT AT MULTAN ROAD LAHORE NEAR MANGA MANDI LHR
See More

Experience

Company Logo
Project Manager
Ravi Green Engineering Pvt. Ltd.
Jan 2019 - Present | Lahore, Pakistan

To lead the project site.
Management of the resources required for the execution of a project.
To ensure the completion of project as per agreed schedule in a safely manner.
To deal with client regarding any issue on site.

Company Logo
Planning & QC Engineer
Ravi Green Engineering Pvt. Ltd.
Apr 2017 - Dec 2018 | Lahore, Pakistan

Preparation of schedule for the execution of project/job.
Preparation & implementation of progress controls/monitoring formats.
Preparation of manpower histogram & resource deployment sheet for a project.
Preparation of recovery schedules for a job.
Prepare & submit BOQ measurement sheets for invoicing of executed scope of work.
Implementation of quality control standards to ensure the execution of job as per agreed standards.
Documentation for implemented controls for quality of job.

Company Logo
PRODUCTION Engineer
Cleveland Bridge & Steel Co.
Apr 2016 - Feb 2017 | Jubail, Saudi Arabia

Planning and Monitoring the production of structural steel and pressure vessels.

Company Logo
Lead Engineer Projects
FAUZ Engineering Limited
Dec 2014 - Apr 2016 | Lahore, Pakistan

to prepare a project plan on P6 for the project activities.
to lead the construction work at project site.
to manage,monitor the execution work and timely provision of resources at construction site.
to report the daily progress and overall status of the site to operations manager.
to liaise with the client for any issue relating the project.

Company Logo
Mechanical Construction Engineer
Special Technical Services LLC Oman
Sep 2012 - Jul 2014 | Muscat, Oman

Detailed drawing study for the job.
Plan the resources and work scope to be executed on daily basis.
Supervise the construction work at site.
communication of site issues to higher management.
Daily meeting with site responsible persons regarding Quality, HSE & Work Progress issues.

Company Logo
Mechanical Engineer
Combined Engineering Pvt. Ltd.
Nov 2010 - Jul 2012 | Karachi, Pakistan

Site Co-ordination for provision of resources
Preparation of work progress reports after taking input from sites.
Development of cost sheets for the projects.
Interaction with clients for there concerns regarding work.

Education

University of Wah
Bachelors, Bachelors in Science, B. Sc Mechanical‎
Mechanical Engineering
CGPA 2.8/4
2010
BISE
Intermediate/A-Level, Faculty of Science (Pre-Engineering), F.Sc (pre-engg.)‎
Maths, Physics, Chemistry
Percentage 61%
2006
K. P. S. I Pre Cadet School
Matriculation/O-Level, Matric in Science, S.S.C‎
Maths, Physics, Chemistry, Computer
Percentage 82%
2003

Skills

Intermediate HSE
Intermediate Inventory Management
Expert Project Management
Intermediate Quality Management
Expert Site Billing
Beginner Civil Planing
Expert Construction Management
Expert Handling Assignments
Intermediate LTN
Expert Social Studies Subject Command

Languages

Expert Punjabi
Expert Urdu
Intermediate Arabic
Expert English

Companies Followed