Professional Engineer (PE) license. Total twenty-six years of experience and fourteen years as a Resident Engineer. led and managed multiple civil engineering projects like Roads Buildings and large infrastructure. Organize and supervise the work of the assigned team to ensure that all work is within a specification, contract agreements, and circulars. I have Project Management Knowledge. Understand the client project work and processing like initiating, planning, executing, Monitoring, Controlling, and Closing processes.
Project based on FIDIC. Report to DTL supervise and manage the site staff assigned to the Contract, and ensure that they carry out their responsibilities and duties, monitor their activities advise the supervision site team on all aspects of construction supervision and quality control. Ensure that all necessary contract documentation is available on-site. Responsible for checking the setting out of all parts of the permanent works before construction, and checking that the work is in accord with the designs after construction. Ensure prompt responses when the Contractor has called for inspections and/or approvals. Liaise regularly with the DTL and provide details of progress and any contractual and technical Problems. Arrange and chair regular meetings with the Contractor and other site staff on scheduled progress and contractual and technical issues that may affect the contractor\'s performance or ability to meet the contract objectives. Review the Contractor\'s initial and updated construction programs for compliance with contract completion dates and ensure that the updated programs properly reflect actual delays and awarded extensions of time. Prepare the Monthly Contract Report and advise The Engineer/Chief Quantity Surveyor of actual and forecast cost and progress of the contract. Submit all bridge piling and foundation records, and girder stressing records, to the B: Eng. Check the adequacy of the Contractor’s temporary works and the safety of the Contractor’s working methods. Review interim payment applications and prepare and approve interim payment certificates for further checking by the chief Quantity Surveyor and certification by The Engineer. Arrange the measurement of works and verify quality compliance of the works. Prepare and maintain Assets Registers for his residency, maintain a record of accidents on site, and notify The Engineer of any serious occurrences. Ensure that the Consultant site staff and the Contractor comply with the requirements of the EMP. Assist in the preparation of “As Built” drawings, a Contractor’s responsibility, coordinate final inspection and acceptance of the work, and prepare a draft completion Certificate for The Engineer to issue.
Project based on FIDIC. PMU Project. Being a Resident Engineer watch and supervise the work and ensure that the standard of workmanship employed follows the specification, contract agreement, and client circular. Ensure Safety compliance, developing Quality Assurance and Quality Control (QA/QC) Plans. Maintain detailed project documentation, reports, and Correspondence letters. Review and negotiate contracts and change orders. Provide technical guidance and support to the project team. Review and monitor the progress of the work according to the project schedule and Provide regular updates and reports to senior management consultants and clients. Determining the measurement and value of work and nominated subcontractor. Meeting with Clients/Consultants regarding future planning and Progress of work and identifying all obstructions and structures that interfere with the right-of-way, in preparation for finding adequate solutions. Prepare a report of a problem at the site like Alligator cracks, La-hi bridge link road, and additional work forward to the engineer and client NHA for proper information and action
Both Project Based on FIDIC.
Activities Perform:
Responsible for project Quantity /Quality, Necessary assessment report. Negotiation, approval of variation orders and reply as per FIDIC, Contract Documents and General Specification.
Relocated and designed Avalanche Gallery /Shot Crete/Culverts/ Protection wall approach to reduce costs, resulting in faster completion by avoiding the main existing services and a cost savings.
Monitoring progress of work according to approved Project schedule and inform contractor about progress from time to time.
Prepare report as per Clauses if there is problem on site and forward to contractor/ Client for proper information and action Earth work Quantity has been adjusted as per actual Rock Classification Approval of Method Statement.
Reviews and Approved works accomplishment, program of works, construction methodologies, as-staked and as-built plans, quality assurance/quality control documents, mobilization/demobilization plan, Interim Payment Certificates and other construction related documents submitted by the Contractor in accordance with the contract provisions and specifications
Activities Performed
Preparing work schadule with C:M work closely with Architect and Engineers to developed Plan.Coordination with consultant, client and approval of execution plan. Negotiating Contract with External Vendors to reach profitable agreement.
Conduct Butt Fusion Test for HDPE Pipe and other Concrete tests.
Briefing to consultant regarding Progress, work done and Two week ahead program.
Monitored and tracked project metrics and collected data to share with project members to identify and quickly address problems.
Maintained tactical control of project budgets and timeline to keep team on task and achieve schedule targets.
Supported senior managers and department leaders by completion projects and problem resolution under tight budgets and schedule
Roads, Bridges, Building Projects Client for all Project was Ministry of Transport Saudi Arabia.
Activities Performed
All road ProjectsBased onFIDIC
Ensured compliance with FIDIC, AASHTO regulation of material testing and design Oversee working of all engineering personnel and inspect all materials and assist to resolve all construction process and recommend improvement to all construction activities an ensure compliance to specifications and construction schedule and prepare all progress reports. IPC, Reply to Contractor Letter with FIDIC, Contract and Specification references
Building, Water Supply, Storm Water Drainage.
Ring Road Kandahar 18 K:m and Shah Agha Road. RCC drain, Storm Water Drainage System
Activities Performed
Preperation and inspection by Consultant of Embankment,Subgrade, ABC AND Asphaltic layer. Stell work and Pourong Process
Excevation from Mainline to Domestic Line and provide service to domestic consumers as per rule of Government of Pakistan.