I did BE in Mechanical engineering from Ned university of engineering and technology in the year 2016, Currently I am working in the Feroze 1888 in Utilities as a S.E.O.
As a Senior Executive Officer in feroze 1888 mills limited
Formulating Annual Preventive Maintenance plan and implement it on weekly basis.
To maintained required parameters/ conditions of boilers as per SPO defined by OEM.
Responsibility for supervision of operators and ensure trouble free operation.
Carrying routine maintenance jobs as per Operations request/complain.
Allocate and suggest maintenance budget for new equipment as per requirement of plant change, increasing needs, increasing efficiency or reducing plant down time in CAPEX (Capital Expenditure) and also suggest reasonable budget for safe and sound operation of existing equipment in OPEX (Operational Expenditure).
Procurement of different parts of boiler equipment’s as per need and safety stock.
Technical evaluation of offers from different vendors.
As a Project Engineer in Petrochemical Engineering Consultant.
To design above ground vertical storage tanks as per API-65
Cost Estimation of the complete project (CAPAX).
Provide technical assistance to the Client related to applicable codes and standards.
Stress Analysis of the existing piping, and proposed piping using Creaser II.
Hydraulic analysis of the complete system to proposed the line size for different purpose.
Assist Draft-man in preparing the oil storage tank drawings according to the requirement of the code.
As an Engineer in Rotary department (June 2019-To present).
1.Formulating Annual Preventive Maintenance plan and implement it on weekly basis.
2.Carrying routine maintenance jobs as per Operations request/complain.
3.Maintaining record on SAP against each maintenance activity of relevant Equipment. Ensure maintenance of safety stock of stock, non-stock and direct charge spares for all types of maintenance of all equipment.
4.Allocate and suggest maintenance budget for new equipment as per requirement of plant change, increasing needs, increasing efficiency or reducing plant down time in CAPEX (Capital Expenditure) and also suggest reasonable budget for safe and sound operation of existing equipment in OPEX (Operational Expenditure).
5.Periodic Vibration analysis of all critical rotary equipment. Perform remedial maintenance on the basis of condition monitoring.
6.Working on equipment reliability, study on failure analysis, mode of failure and meantime between failures (MTBF).
7.Procurement of different parts of rotary equipment’s as per need and safety stock.
8.Technical evaluation of offers from different vendors.
As an Engineer in Construction department (May-2018 to May-2019).
1.Plan, Organize and assets site supervisor for execution of construction activities of the project according to the schedule.
2.Prepare BOQ of completed Project.
3.Prepare ITT (Invitation To Tender).
4.Technical Evaluation of different offers from different vendors.
5.Cost Estimation of the complete project (CAPEX).
6.To ensure that the tank construction is according to standards API 650 and 653.
7.Prepare contractors invoices.
8.To review technical drawings and assets site supervisor.
9.Team lead for the major repair and new construction of 120 ft dia. Crude oil storage tanks.