An Experienced Professional (Civil) Engineer with more than 17 years of versatile professional experience in the field of building construction & infra-structure in public & private sectors, which includes Project planning/approval & management, Procurement/Contracts administration & management for Works/Services/Goods, PC-I(Project Document) & PC-II preparation & approval, Detail/Top construction supervision, Project estimation & budgeting, Quality control, progress review/control & maintenance of completed facilities etc. I have successfully handled projects from planning to completion phase with strict compliance to project’s specifications, timelines & budget.
(World Bank Funded Khyber Pakhtunkhwa Hydropower & Renewable Energy Development Program) - (88 MW Gabral Kalam HPP & 157 MW Madyan HPP = USD 600 Million Project Cost )
§ Preparation & review of PQD (Pre-qualification Documents)
§ Preparation and review of Pre-qualification Evaluation Reports for Prequalification of Contractors
§ Preparation & review of RFP’s (Request for Proposals) for Procurement of Services
§ Preparation & review of Technical/Financial Proposals Evaluation Reports for hiring of Sub-Consultants
§ Preparation & review of Bidding documents for Procurement of Civil/E&M Works Contracts
§ Preparation of Minutes of Meeting for Pre-Bid Meetings & for Bid Opening
§ Preparation and review of PPSD & Procurement Plans
§ Preparation of Clarifications to Bidding Documents for issuance to Bidders
§ Preparation & review of Bidding Documents for Procurement of Goods
§ Preparation and review of Bid Evaluation Reports for Procurement of Civil/E&M Works and Goods Contracts
§ Preparation & review of Addendum to Bidding Documents
§ Preparation & review of Variation orders
§ Contract interpretations
§ Preparation and review of amendments to Contract(s)
§ Review of Engineer's decision
§ Preparation & review of Memorandum of Understanding (MoU), Joint Venture/Consortium Agreements, etc.
§ Preparation and review of Contracts for Consultancy Services
§ Review of Contractor’s EOT (Extension of Time) & Additional Cost Claims
§ Preparation & review of Taking Over Certificates (TOC) as per Contract
§ Used World Bank’s Standard Forms of Bidding Documents
(World Bank Funded Khyber Pakhtunkhwa Hydropower & Renewable Energy Development Program) - (88 MW Gabral Kalam HPP & 157 MW Madyan HPP)
§ Preparation & review of PQD (Pre-qualification Documents)
§ Preparation and review of Pre-qualification Evaluation Reports for Prequalification of Contractors & Consultants
§ Preparation & review of RFP’s (Request for Proposals) for Procurement of Services including drafting/review of RFP advertisement Notice, Instructions to Applicants, detailed evaluation criteria along with standard technical/financial proposals application forms, detailed ToR’s (Terms of References) & proposed standard form of Consultancy Contract
§ Preparation & review of Technical/Financial Proposals Evaluation Reports for hiring of Consultants
§ Preparation & review of Bidding documents for Procurement of Civil/E&M Works and Goods Contracts
§ Preparation of Minutes of Meeting for Pre-Bid Meetings & for Bid Opening
§ Preparation and review of PPSD & Procurement Plans
§ Preparation of Clarifications to Bidding Documents for issuance to Bidders
§ Preparation and review of Bid Evaluation Reports for Procurement of Civil/E&M Works Contracts and Goods Contracts
§ Preparation & review of Addendum to Bidding Documents
§ Preparation & review of Variation orders
§ Contract interpretations
§ Preparation and review of amendments to Contract(s)
§ Review of Engineer's decision
§ Preparation & review of Memorandum of Understanding (MoU), Joint Venture/Consortium Agreements, etc.
§ Preparation and review of Contracts for Consultancy Services
§ Review of Contractor’s EOT (Extension of Time) & Additional Payment Claims
Planning and designing of short and long term development plans of the University.
Managing & leading all Development Projects of University from inception till completion
Co-ordination with Teaching & Non-Teaching Departments relevant to Infrastructure Development.
Managing Preparation, submission & approval of PC-II for Feasibility Studies of Civil Developmental Projects.
Managing the Consultants hiring process from pre-qualification till award of Contract
Managing the Design phase and dealing with the Consultants on behalf of University Leadership
Managing preparation, submission and approval of Development Projects (PC-I)
Planning & managing the development budget
Managing procurement of Works/Goods from pre-qualification till award of Contract
Co-ordination with donor agencies, Ministry/Division for approval of scheme and release of funds.
Contract Administration & Management of all awarded contracts of works, services & goods.
Co-ordination with University bodies such as, Syndicate, Senate, etc.
Managing preparation & submission PC-III & PC-IV of Development Projects
Coordination with HEC, Ministries & other departments regarding Development Projects
Preparation of Pre-qualification & Bidding Documents for Procurement of Works, Services & Goods
Preparation of Addenda to Bidding Documents
Preparation & review of Conditions of Contract for Works, Services & Goods Contracts
Preparation & review of Pre-qualification Evaluation Reports
Preparation & review of Bid Evaluation reports and assistance
Contract’s interpretations
Review of Amendments to Contract(s)
Review of Engineer's Decision
Preparation of Taking Over Certificates (TOC) & Defects Liability Certificates (DLC)
Preparation & Approval of Variation orders
Preparation & review of Memorandum of Understanding (MoU), Joint Venture/Consortium Agreements, etc.
Review & Approval of Contractor’s EOT(Extension of Time) & Additional Payment Claims
Contract Management/Administration of Capital & Maintenance Projects
Standard Forms of Bidding Documents & Contracts used are of PEC & FIDIC
§ Preparation & review of PQD (Pre-qualification Documents) for Prequalification of Contractors & Sub-Consultants including drafting of Invitation for Prequalification, Letter of Application, Instructions to Applicants & detailed evaluation criteria along with standard application forms etc.
§ Preparation and review of Pre-qualification Evaluation Reports for Prequalification of Contractors & Consultants
§ Preparation & review of RFP’s(Request for Proposals) for Procurement of Services including drafting/review of RFP advertisement Notice, Instructions to Applicants, detailed evaluation criteria along with standard technical/financial proposals application forms, detailed ToR’s (Terms of References) & proposed standard form of Consultancy Contract
§ Preparation & review of Technical/Financial Proposals Evaluation Reports for hiring of Sub-Consultants
§ Preparation & review of Bidding documents for Procurement of Civil/E&M Works Contracts and Turnkey (EPC) Contracts including review of Invitation for Bids, Instruction to Bidders with Bidding Data, Forms of Technical/Price Bids with Schedules to Bids, Conditions of Contract (GCC & PCC), Schedule of Prices, Standard Forms, Specifications & Drawings etc.
§ Preparation & review of Bidding Documents for Procurement of Goods
§ Preparation and review of Bid Evaluation Reports for Procurement of Civil/E&M Works Contracts, EPC and Goods Contracts
§ Preparation & review of Addendum to Bidding Documents
§ Preparation & review of Variation orders
§ Contract interpretations
§ Preparation and review of amendments to Contract(s)
§ Review of Engineer's decision
§ Preparation & review of Memorandum of Understanding (MoU), Joint Venture/Consortium Agreements, etc.
§ Preparation and review of Contracts for Consultancy Services
§ Review of Contractor’s EOT(Extension of Time) & Additional Payment Claims
§ Preparation & review of Taking Over Certificates (TOC) as per Contract
§ Standard Forms of Bidding Documents & Contracts used are of PEC, FIDIC, World Bank & ADB etc.
(Major Project’s Assignments: -102 MW Gulpur Hydro Power Project,Mangla Dam Raising Project & Mohmand Dam Project etc.)
§ Planning and scheduling the development activities of the university including master planning, detail designing and construction as per PC-1 targets.
§ Preparation & review of Civil Works component of PC-1 of public sector universities
§ Pre-Qualification of Consultants (Region & Category wise) throughout Pakistan for HEC funded developmental projects of Universities/HEI’s Including preparation/approval of EOI (Expression of Interest), PQD (Pre-qualification Document) & Technical evaluation as per PQD’s pre-defined evaluation criteria
§ Preparation & review of RFP (Request for Proposals) for hiring/recruitment of Consultants including drafting/review of RFP advertisement Notice, Instructions to Applicants, detailed evaluation criteria along with standard technical/financial proposals application forms, detailed ToR’s (Terms of References) & proposed standard form of Consultancy Contract
§ Review of Procurement process of consultants & contractors for HEC funded developmental projects of universities on behalf of HEC as per PEC/PPRA procurement guidelines.
§ Review of Contract documents to be executed with consultants & contractors for HEC funded developmental projects of HEI’s
§ Preparation & review of Prequalification and Tender/Bidding documents for hiring/recruitment of Contractors
§ Generation of Project Profile in PMES (Project Monitoring & Evaluation System) of Planning Commission, Pakistan followed by updating of Work Plan & Cash Plans on quarterly/annual basis
§ Top supervision on HEC funded developmental projects of HEI’s
§ Performed as member of Technical Committee constituted for Evaluation of Technical & Financial Proposals for Procurement of Works & Services for HEC funded developmental projects of HEI’s/universities
§ Award of contract to successful consultants & contractors
§ Performed as member of Building Design Review Committee constituted for review/approval of preliminary/conceptual designs of buildings & Master Plan proposed by the consultant for HEC funded developmental projects of HEI’s
§ Monitoring, periodic reviews of project progress, updating and control.
§ Coordination with the consultant & contractor on behalf of senior management
§ Contract Management& Administration
§ Approval/payments to consultant & contractor as per the Contract Agreement
§ Project’s feasibility, estimation & Approval
§ Delivering the Project from inception to Completion
§ Planning, procurement, contract management, execution, supervision & maintenance of works.
§ Procurement of Consultancy Services, Civil Works & Goods
§ Preparation & review of Bidding Documents, RFPs & PQD
§ Review/drafting of Conditions of Contract for Works, Goods & Services Contracts
§ Dealing with all contractors and consultants on behalf of senior management
§ Assurance of Quality as defined in technical specifications.
§ Detail supervision on contractor’s & supervisory staff
§ Presenting the Monthly Progress Reports in Quarterly Progress review meetings.
§ Approval of Interim & Final Payment Certificates
§ Ensuring the completion of project within approved timeline and budget
§ Variation orders Approval
§ Rate Analysis Approval
§ Handing-Taking proceedings/Approval of Completed Works
§ Maintenance of Handed over works
§ Led a maintenance team with 50 staff strength comprising of engineers, sub-engineers, tradesmen & un-skilled staff.
§ Responsible for the complete development & maintenance works of the facility spreading over the area of 12,000 Kanals.
§ Detailed Construction Supervision of works.
§ Assisting the client in planning, procurement, contract management, execution & supervision of works.
§ Preparation & review of Bidding documents
§ Review/drafting of Conditions of Contract
§ Carry out site surveys for layout of works.
§ Soil investigation for foundations of various structures.
§ Checking & vetting of IPCs (RARs) and final bills.
§ Checking & vetting of Variation Orders, Rate Analysis, Bar-bending Schedules & Shop Drawings.
§ Checking of Work diary, Field density test reports & Check requests.
§ Preparation of Monthly Progress Reports.
§ Review of all construction drawings prior to it’s issuance to contractors.
§ Quality Assurance of works as per Technical Specifications.
§ Assisting the client in preparation of engineer estimates & PC-I, when required.
Technical input to client regarding any matter pertaining to project.
§ Managing rehabilitation & restoration of Water Supply & Sanitation Schemes in Earth Quake affected Areas Undertaken by IMC
§ Preparation of Initial & Detail Assessment Reports for rehabilitation and restoration of above Schemes
§ Supervision of above Schemes by making frequent and long distant visits to sites
§ Representation of Organization in Cluster Meetings held under umbrella of Unicef for detail description of the current status of all Watsan sites undertaken by IMC
§ Requisition of materials required for Schemes as per Detail Assessment Report
§ Maintaining Logistic Record of all the materials Pro-cured/not Pro-cured as per
requisitions and supplied to sites in Collaboration with Logistic Officer
§ Supply of Material to Sites As per Detail Assessment
§ Progress Report Preparation of all the Schemes
§ Dealing with the Communities for motivating and encouraging them to help themselves for the Restoration of Watsan Schemes
§ Involving the Community to work for their selves by giving them incentives like cash for work and Hygiene Kits Supplied through our Hygiene Promotion Team.
Site supervision.
Check Survey.
Quality control.
IPC’s checking.
Bar-Bending Schedule Checking and Approval
Quantities Computation & Verification
Preparation of As Built Drawings