概要

Responsibilities:

Technical evaluation of bids of Projects. Reviewed the manufacturing experience, satisfactory operation certificates and type test reports of the equipment manufacturers as per the guidelines of Financing Agency.

Financial evaluation of bids of Projects. Reviewed in detail financial turnover, contractual aspects, qualification analysis of the bidders.

Preparation of technical and financial bid evaluation reports and award of the contract to the qualified bidder

Finalization of contract documents and recommended requisite information, including compiling/documentation of all the technical and commercial clarifications with contractors

Preparation of layouts, base design and schematic drawings. Assisted the design review specialty team in finalization of detail design as per technical specifications and international standards.

Equipment Design review of 250 MVA Auto-Transformers, 6.3 MVA Power Transformers, 500/220/132kV and 220/123kV Circuit Breaker, Disconnectors, Transformer, CT’s, CCVT’s, Line Traps.

Equipment Procurement that includes Technical and Commercial evaluation of offers from various suppliers in compliance with technical specifications of Contract & order finalization.

Preparation of amendments, EOT cases, contract agreements and variation orders for project.

Establishing, monitoring and control of Scope & Schedule Change Control process of the Projects

Prepared daily, weekly and monthly time schedules, keeping in view the Projects completion schedule.

Communicating letters/reminders to the Contractor and Client, preparing Bar-Charts, Time sheets, Disbursement forecast and progress reports for the Projects.

Carrying out Site visits on regular basis and checking the facilities are done as per approved drawings, also
checking the regularity of health and safety measures are as per international standards.

Attending testing and commissioning and preparing Project Completion Report.

项目

Extension Works at 500kV Ghakkar and Muzaffargarh Substation
Mansehra 220kV Substation Project (Project Engineer)
Gujrat 220kV Substation Project (Project Engineer)
500kV New Lahore Substation Project (Bid Evaluation and Report Writing)

工作经历

公司标识
Senior Engineer/Projects Engineer
National Engineering Services Pakistan (Pvt.) Ltd. (NESPAK)
May 2011 - Sep 2017 | Lahore, Pakistan

Project (JICA Funded, 2.6 Billion Rupees):
Design, Supply, Installation, Testing and Commissioning of 500kV New Lahore Substation Project

Achievement:
Technical and Financial Evaluation of Bids, preparation of evaluation reports. Project Engineering, Contracts Management

Project (JICA Funded, 1.8 Billion Rupees):
Design, Supply, Installation, Testing and Commissioning of 220kV Gujrat 220kV Substation Project

Achievement:
Responsible for Project, engineering, monitoring and execution from bidding stage till completion of the Project

Project (ADB Funded, 1.6 Billion Rupees):
Design, Supply, Installation, Testing and Commissioning of 220kV Mansehra Substation project

Achievement:
Responsible for construction supervision , design review and project execution from bidding stage till completion.

Project (ADB Funded, 750 Million Rupees):
Extension works at 500kV Ghakkar and Muzaffargarh Substation project

Achievement:
Responsible for Project planning, contracts management, design preparation and execution

学历

University Of Engineering & Technology Taxila
学士, Bachelors in Engineering, B.E Electrical Engineering‎
Electrical Power
所占比重 63%
2010

技能

熟练 Contracts Management
熟练 End To End Project Management
熟练 Evaluation of Technical & Financial Bid
熟练 Project Engineering
熟练 Project Scope, Cost and Time Planning
熟练 Strong writing skill

语言

熟练 英语